Company Experience
AMPHASTAR PHARMACEUTICAL, INC.
INJECTABLE PHARMACEUTICAL CLEANROOM MANUFACTURING FACILITY
Cleanroom areas - ISO 5, 7 & 8 (Class 100,
10,000 & 100,000) 10,163 Sq./Ft.
Total Project Build-out 10,163 Sq./Ft.
SCOPE: PROVIDED COMPLETE DESIGN AND TURN-KEY CONSTRUCTION
OF THE CLEANROOM MANUFACTURING FACILITY
1. Complete engineering design of architectural,
structural, electrical, plumbing, fire protection, process
mechanical, HVAC mechanical and all necessary support
utilities
2. CAD drawings - floor plan, site plan, sections,
ceiling plan, electrical, mechanical layouts, DI system,
CDA/VAC system, process water, waste treatment, bulk
gases, high purity gases and HVAC equipment & chiller
plant
3. Documents for and executed by city permit process
4. Project management to manage all phases of engineering,
procurement, subcontractor qualifications, site management,
start-up, test & balance of mechanical systems and
certification
5. Construction management to manage all phases
of construction, including demolition, cleanroom walls,
ceilings, flooring, plumbing, HVAC & process mechanical,
concrete, structural and electrical
6. Commissioning and cleanroom certification for
compliance per Federal Standard 209E
7. Detailed Turn-over package
BROOKS AUTOMATION
IC FAB EQUIPMENT MANUFACTURING & TESTING FACILITY
Cleanroom areas - ISO 6 & 7 (Class 1,000 & 10,000)
10,163 Sq./Ft.
All other areas (non-cleanroom) 24,460 Sq./Ft.
Total Project Build-out 39,580 Sq./Ft.
SCOPE: PROVIDED COMPLETE DESIGN AND TURN-KEY CONSTRUCTION
OF THE CLEANROOM FACILITY, INCLUDING TENANT IMPROVEMENT
AND ALL OTHER SUPPORT AREAS
1. Complete engineering design of demolition, architectural,
structural, electrical, plumbing, fire/life saftey, process
untilties, HVAC mechanical and all necessary support
utilities
2. CAD drawings - floor plan, site plan, sections,
ceiling plan, electrical, mechanical layouts, RO system,
process utilities, HVAC equipment & chiller plant
3. Documents for and executed by city permit process
4. Project management to manage all phases of engineering,
procurement, subcontractor qualifications, site management,
start-up, test & balance of mechanical systems and
certification
5. Construction management to manage all phases
of construction, including demolition, cleanroom walls,
ceilings, flooring, plumbing, HVAC & process mechanical,
concrete, structural and electrical
6. Commissioning and cleanroom certification for
compliance per Federal Standard 209E
7. Detailed Turn-over package
DIGILENS, INC.
IC PILOT PLANT FOR WAVE GUIDE TECHNOLOGY
Cleanroom areas - ISO 5 & 7 (Class 100 & 10,000)
4,738 Sq./Ft.
All other areas (non-cleanroom) 4,875 Sq./Ft.
Total Project Build-out 9,613 Sq./Ft.
SCOPE: PROVIDED COMPLETE DESIGN AND TURN-KEY CONSTRUCTION
OF THE H6 LEVEL CLEANROOM FACILITY, INCLUDING TENANT
IMPROVEMENTS
1. Team approach for complete engineering design
of demolition, architectural, structural, electrical,
plumbing, fire protection, process mechanical, HVAC mechanical
and all necessary support utilities
2. CAD drawings - floor plan, site plan, sections,
ceiling plan, electrical, mechanical layouts, DI system,
CDA/VAC system, process water, waste treatment, gas bunkers,
bulk gases, high purity gas delivery, electric switch
gear/substation, back-up generator and HVAC equipment & chiller
plant
3. Documents for and executed by city permit process
4. Project management to manage all phases of engineering,
procurement, subcontractor qualifications, site management,
start-up, test and balance of mechanical systems and
clean room certification
5. Construction management to manage all phases
of construction, including demolition, cleanroom walls,
ceilings, flooring, plumbing, HVAC & process mechanical,
gas bunkers, concrete, structural and electrical
6. Commissioning and cleanroom certification for
compliance per Federal Standard 209E
7. Detailed turn-over package
HEMACARE INC.
BLOOD ANTIBODY PROCESS FACILITY
Cleanroom areas - ISO 5, 7 & 8 (Class 100,
10,00 & 100,000) 9,560 Sq./Ft.
Total Project Build-out 9,560 Sq./Ft.
SCOPE: PROVIDED COMPLETE DESIGN AND TURN-KEY CONSTRUCTION
OF THE CLEANROOM FACILITY
1. Complete engineering design of architectural,
structural, electrical, plumbing, fire protection, process
mechanical, HVAC mechanical and all necessary support
utilities
2. CAD drawings - floor plan, site plan, sections,
ceiling plan, electrical and mechanical layouts
3. Documents for and executed by city permit process
4. Project management to manage all phases of engineering,
procurement, subcontractor qualifications, site management,
start-up, test and balance of mechanical systems and
clean room certification
5. Construction management to manage all phases
of construction, including demolition, cleanroom walls,
ceilings, flooring, plumbing, HVAC & process mechanical,
gas bunkers, concrete, structural and electrical
6. Commissioning and cleanroom certification for
compliance per Federal Standard 209E
7. Detailed turn-over package
INTERNATIONAL MEDICAL SYSTEMS
PHARMACEUTICAL MANUFACTURING FACILITY
Cleanroom areas - ISO 5, 6, 7 & 8 (Class 100,
1,000, 10,000 & 100,000) 7,892 Sq./Ft.
Total Project Build-out 7,892 Sq./Ft.
SCOPE: PROVIDED COMPLETE DESIGN AND TURN-KEY CONSTRUCTION
OF THE CLEANROOM MANUFACTURING FACILITY
1. Complete engineering design of architectural,
structural, electrical, plumbing, fire protection, process
mechanical, HVAC mechanical and all necessary support
utilities
2. CAD drawings - floor plan, site plan, sections,
ceiling plan, electrical, mechanical layouts, High Purity
process water, CDA/VAC system and HVAC equipment & chiller
plant, boiler
3. Documents for and executed by city permit process
4. Project management to manage all phases of engineering,
procurement, subcontractor qualifications, site management,
start-up, test & balance of mechanical systems and
certification
5. Construction management to manage all phases
of construction, including demolition, cleanroom walls,
ceilings, flooring, plumbing, HVAC & process mechanical,
concrete, structural and electrical
6. Commissioning and cleanroom certification for
compliance per Federal Standard 209E
7. Detailed Turn-over package
INDUSTRIAL CIRCUITS
ELECTRIC CIRCUIT BOARD MANUFACTURING FACILITY
Cleanroom areas - ISO 7 & 8 (Class 10,00 & 100,000)
9,400 Sq./Ft.
Total Project Build-out 9,400 Sq./Ft.
SCOPE: PROVIDED COMPLETE DESIGN AND TURN-KEY CONSTRUCTION
OF THE CLEANROOM FACILITY
1. Complete engineering design of architectural,
structural, electrical, plumbing, fire protection, process
mechanical, HVAC mechanical and all necessary support
utilities
2. CAD drawings - floor plan, site plan, sections,
ceiling plan and mechanical layouts
3. Documents for and executed by city permit process
4. Project management to manage all phases of engineering,
procurement, subcontractor qualifications, site management,
start-up, test and balance of mechanical systems and
clean room certification
5. Construction management to manage all phases
of construction, including cleanroom walls, ceilings,
flooring, HVAC & process mechanical, structural and
electrical
6. Commissioning and cleanroom certification for
compliance per Federal Standard 209E
7. Detailed Turn-over package
KYOCERA AMERICA, INC.
ELECTRONIC HYBRID MANUFACTURING FACILITY
Cleanroom areas - ISO 7 & 8 (Class 10,00 & 100,000)
10,000 Sq./Ft.
Total Project Build-out 10,000 Sq./Ft.
SCOPE: PROVIDED COMPLETE DESIGN AND TURN-KEY CONSTRUCTION
OF THE CLEANROOM FACILITY
1. Complete engineering design of architectural,
structural, electrical, plumbing, fire protection, process
mechanical, HVAC mechanical and all necessary support
utilities
2. CAD drawings - floor plan, site plan, sections,
ceiling plan and mechanical layouts
3. Documents for and executed by city permit process
4. Project management to manage all phases of engineering,
procurement, subcontractor qualifications, site management,
start-up, test and balance of mechanical systems and
clean room certification
5. Construction management to manage all phases
of construction, including cleanroom walls, ceilings,
flooring, HVAC & process mechanical, structural and
electrical
6. Commissioning and cleanroom certification for
compliance per Federal Standard 209E
7. Detailed Turn-over package
McCLELLAN AIR FORCE BASE
IC MANUFACTURING FACILITY (Weapons Systems Semiconductor
Fab)
Cleanroom areas - ISO 4, 5 & 7 (Class 10, 100 & 1,000)
3,956 Sq./Ft.
Total Project Build-out 3,956 Sq./Ft.
SCOPE: PROVIDED COMPLETE DESIGN AND TURN-KEY CONSTRUCTION
OF THE H6 LEVEL CLEANROOM FACILITY
1. Complete engineering design of architectural,
structural, electrical, plumbing, fire protection, process
mechanical, gas detection, HVAC mechanical and all necessary
support utilities
2. CAD drawings - floor plan, site plan, sections,
ceiling plan, mechanical layouts, DI system, CDA/VAC
system, process water, waste treatment, bulk gases, high
purity gases, electric switch gear/substation, back-up
generator and HVAC equipment/chiller plant
3. Documents for and executed by city permit process
4. Project management to manage all phases of engineering,
procurement, subcontractor qualifications, site management,
start-up, test and balance of mechanical systems and
clean room certification
5. Construction management to manage all phases
of construction, including demolition, cleanroom walls,
ceilings, flooring, plumbing, HVAC & process mechanical,
gas bunkers, concrete, structural and electrical
6. Commissioning and cleanroom certification for
compliance per Federal Standard 209E
7. Detailed Turn-over package
MOS ELECTRONICS TAIWAN INC.
SDRAM & SPECIAL MEMORY CHIP MANUFACTURING FACILITY
Cleanroom areas - ISO 3, 5, 6, 7 & 8 (Class
1, 100, 1,000, 10,000 & 1000,000) 57,000 Sq./Ft.
Total Project Build-out 57,000 Sq./Ft.
SCOPE: PROVIDED PRELIMINARY DESIGN, DEVELOPMENT, ENGINEERING
AND COMPLETE BID SPECIFICATION PACKAGE
1. CAD drawings - floor plan, site layout, mechanical
layout, sections and air flow schematics
2. Engineering tables for recirculation air, make-up
air, exhaust air, static pressure, KW/horsepower requirements,
annual operating costs, heating/cooling loads and ventilation
loads
3. Electrical load summary for HVAC, lighting,
process and support systems, office electrical and emergency
power requirements
4. Block space drawings for DI system, CDA/VAC
system, process water, waste treatment, bulk gases, high
purity gases, electric switch gear/substation and HVAC
equipment/chiller plant
5. Preliminary construction budget and material/equipment
recommended vendors
6. Process equipment detailed requirement tables
for exhaust air, electrical, process cooling water, DI
water, ultra pure gases, CDA/VAC and other utility requirements
7. Schematic CAD drawings for process piping, exhaust,
electrical and HVAC piping
8. Recommendations for safety considerations per
Uniform Building Code (UBC), National Fire Code (NFC)
and Hazardous Materials Handling per (UBC H-6)
NELCO PRODUCTS
PRINTED CIRCUIT BOARD MANUFACTURING
Cleanroom areas - ISO 5, 7 & 8 (Class 100,
10,000 & 100,000) 10,163 Sq./Ft.
Total Project Build-out 10,163 Sq./Ft.
SCOPE: PROVIDED COMPLETE DESIGN AND TURN-KEY CONSTRUCTION
OF THE CLEANROOM FACILITY, INCLUDING SUPPORT AREAS
1. Complete engineering design of architectural,
structural, electrical, process mechanical, HVAC mechanical
and all necessary support utilities
2. CAD drawings - floor plan, site plan, sections,
ceiling plan, electrical, mechanical layouts, DI system,
CDA/VAC system, process water, waste treatment, bulk
gases, high purity gases and HVAC equipment & chiller
plant
3. Documents for and executed by city permit process
4. Project management to manage all phases of engineering,
procurement, subcontractor qualifications, site management,
start-up, test & balance of mechanical systems and
certification
5. Construction management to manage all phases
of construction, including demolition, cleanroom walls,
ceilings, flooring, plumbing, HVAC & process mechanical,
concrete, structural and electrical
6. Commissioning and cleanroom certification for
compliance per Federal Standard 209E
7. Detailed Turn-over package
SEAGATE MAGNETICS (QUINTA)
DISK DRIVE MANUFACTURING FACILITY
Cleanroom areas - ISO 5 (Class 100) 4,200 Sq./Ft.
Total Project Build-out 4,200 Sq./Ft.
SCOPE: PROVIDED COMPLETE DESIGN AND TURN-KEY CONSTRUCTION
OF THE CLEANROOM FACILITY
1. Complete engineering design of architectural,
structural, electrical, process mechanical, HVAC mechanical
and all necessary support utilities
2. CAD drawings - floor plan, site plan, sections,
ceiling plan and mechanical layouts
3. Documents for and executed by city permit process
4. Project management to manage all phases of engineering,
procurement, subcontractor qualifications, site management,
start-up, test and balance of mechanical systems and
clean room certification
5. Construction management to manage all phases
of construction, including cleanroom walls, ceilings,
flooring, HVAC & process mechanical, structural and
electrical
6. Commissioning and cleanroom certification for
compliance per Federal Standard 209E
7. Detailed Turn-over package
SEMCO LASER TECHNOLOGY
MOCVD FACILITY
Cleanroom areas - ISO 4, 5 & 6 (Class 10, 100 & 1,000)
3,956 Sq./Ft.
Total Project Build-out 3,956 Sq./Ft.
SCOPE: PROVIDED DESIGN REVIEW, ENGINEERING AND
TURN-KEY CONSTRUCTION OF THE H6 LEVEL CLEANROOM FACILITY,
INCLUDING TENANT IMPROVEMENTS. H6 LEVEL CONSTRUCTION
1. Team approach for complete engineering design
of demolition, architectural, structural, electrical,
process mechanical, HVAC mechanical and all necessary
support utilities
2. CAD drawings - floor plan, site plan, sections,
ceiling plan, mechanical layouts, DI system, CDA/VAC
system, process water, waste treatment, bulk gases, high
purity gases, electric switch gear/substation, back-up
generator and HVAC equipment/chiller plant
3. Documents for and executed by city permit process
4. Project management to manage all phases of engineering,
procurement, subcontractor qualifications, site management,
start-up, test and balance of mechanical systems and
clean room certification
5. Construction management to manage all phases
of construction, including demolition, cleanroom walls,
ceilings, flooring, plumbing, HVAC & process mechanical,
gas bunkers, concrete, structural and electrical
6. Commissioning and cleanroom certification for
compliance per Federal Standard 209E
7. Detailed Turn-over package
UNIT INSTRUMENTS
MASS FLOW METER MANUFACTURING FACILITY
Cleanroom areas - ISO 5, 7 & 8 (Class 100,
10,000 & 100,000) 12,560 Sq./Ft.
Total Project Build-out 12,560 Sq./Ft.
SCOPE: PROVIDED COMPLETE DESIGN AND TURN-KEY CONSTRUCTION
OF THE CLEANROOM FACILITY
1. Complete engineering design of architectural,
structural, electrical, process mechanical, HVAC mechanical
and all necessary support utilities
2. CAD drawings - floor plan, site plan, sections,
ceiling plan and mechanical layouts
3. Documents for and executed by city permit process
4. Project management to manage all phases of engineering,
procurement, subcontractor qualifications, site management,
start-up, test and balance of mechanical systems and
clean room certification
5. Construction management to manage all phases
of construction, including cleanroom walls, ceilings,
flooring, HVAC & process mechanical, structural and
electrical
6. Commissioning and cleanroom certification for
compliance per Federal Standard 209E
7. Detailed Turn-over package
|